Which statement about baselines in performance measurement is true?

Get ready for the CMPM Exam with our quiz. Test your knowledge with multiple choice questions, each with detailed explanations and hints. Prepare effectively for a successful exam day!

Multiple Choice

Which statement about baselines in performance measurement is true?

Explanation:
Baselines are the approved reference points used to measure project performance. They set the expected scope, schedule, and cost. By comparing actual work, timing, and spending to these baselines, you can see variances that indicate deviations. Those variances trigger management actions and help forecast future performance. Baselines are established and approved during planning and are not optional once execution begins. They are the yardstick for performance; actual results will differ, but variation is what you monitor.

Baselines are the approved reference points used to measure project performance. They set the expected scope, schedule, and cost. By comparing actual work, timing, and spending to these baselines, you can see variances that indicate deviations. Those variances trigger management actions and help forecast future performance. Baselines are established and approved during planning and are not optional once execution begins. They are the yardstick for performance; actual results will differ, but variation is what you monitor.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy